CTH VV (PIONEER RD) from Hickory Street to Rogersville Road
Schedule: April 2017 thru November 2017
Description: This project will include the reconstruction of CTH VV (Pioneer Road) from Hickory Street to Rogersville Road. The signalized intersection at Pioneer Road and Military Road will be converted to a roundabout. Work will include grading, watermain, sanitary sewer, storm sewer, base aggregate, concrete pavement, curb and gutter, and sidewalk, traffic signals, signing, pavement marking, lighting and landscaping.
May 15th to May 19th: The contractor will continue grading on the southbound lanes of Military Road south of CTH VV and also the west end of the project on CTH VV (Pioneer Road). Breaker run and base aggregate will be placed on Sullivan Drive. The contractor will continue work on the storm sewer along CTH VV (Pioneer Road) west of Military Road.
Traffic impacts: CTH VV (Pioneer Road from Hickory Street to Triangle Road and Military Road from the IH 41 off ramps to CTH VV (Pioneer Road) will be closed to thru traffic. CTH VV (Pioneer Road) will have a signed detour via STH 23 (Johnson Street) to IH 41 to Hickory Street. There will also be a signed detour for Military Road via IH 41 to Hickory Street. Detour signage will be installed along IH 41 directing northbound Military Road traffic to the Hickory Street interchange, at which point traffic will follow the signed detour along Hickory Street. Access through the construction site to Sullivan Drive and Rogersville Road may be limited at times. Access to businesses will be maintained. Military Road has one lane in each direction south of CTH VV (Pioneer Road).
Seventh Street from South Main Street to South Park Avenue
Schedule: May 2017 to September 2017
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
May 15th to May 19th: The utility contractor will start street excavation.
Traffic Impacts: Seventh Street will be closed to through traffic mid-week. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.
North Military Road from West Follett Street to West Scott Street
Schedule: May 2017 to September 2017
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
May 15th to May 19th: Crews for Alliant Energy continue to install gas main and making service connections.
Traffic Impacts: Military Road remains open to traffic.
Fifth Street from South Marr Street to South Park Avenue
Schedule: May 2017 to September 2017
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
May 15th to May 19th: Crews for Alliant Energy will be installing gas main and making service connections. The tree removal contractor is working to remove terrace trees.
Traffic Impacts: Fifth Street remains open to traffic.
Ellis Street from Fourth Street to Eight Street (North Leg)
Schedule: May 2017 to September 2017
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
May 15th to May 19th: Crews for Alliant Energy will be installing gas main and making service connections. The tree removal contractor is working to remove terrace trees.
Traffic Impacts: Ellis Street remains open to traffic.