Seventh Street from South Main Street to South Park Avenue
Schedule: May 2017 to November 2017
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
August 14th to August 18th: The paving contractor will continue to pour curb and gutter and follow behind pouring driveway aprons and sidewalks.
Traffic Impacts: Seventh Street is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.
North Military Road from West Follett Street to West Scott Street
Schedule: May 2017 to November 2017
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
August 14th to August 18th: The utility contractor will continue to install sanitary sewer main from McWilliams Street to the south.
Traffic Impacts: Military Road is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.
Fifth Street from South Marr Street to South Park Avenue
Schedule: May 2017 to November 2017
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
August 14th to August 18th: The utility contractor has completed the sanitary sewer, water main and laterals and will continue installing storm sewer main and laterals.
Traffic Impacts: Fifth Street is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.
Ellis Street from Fourth Street to Eight Street (North Leg)
Schedule: May 2017 to November 2017
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
August 14th to August 18th: The utility contractor has completed the sanitary sewer, water main and laterals on Ellis Street from Fourth Street to Sixth Street and will continue installing storm sewer main and laterals. The paving contractor continues placing curb and gutter, driveway aprons and sidewalks from Sixth Street to Eighth Street.
Traffic Impacts: Ellis Street is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.
CTH VV (PIONEER RD) from Hickory Street to Rogersville Road
Schedule: April 2017 thru November 2017
Description: This project will include the reconstruction of CTH VV (Pioneer Road) from Hickory Street to Rogersville Road. The signalized intersection at Pioneer Road and Military Road will be converted to a roundabout. Work will include grading, water main, sanitary sewer, storm sewer, base aggregate, concrete pavement, curb and gutter, and sidewalk, traffic signals, signing, pavement marking, lighting and landscaping.
August 21st to August 25th: The contractor is scheduled to place concrete curb and gutter along the eastbound lanes of CTH VV (Pioneer Road) between Military Road and Hickory Street. Watermain and sanitary sewer will be placed on Military Road between CTH VV (Pioneer Road) and the north project limits. Landscaping work may be done on CTH VV (Pioneer Road) west of Military Road. The contractor will also continue grading for the westbound lanes of CTH VV (Pioneer Road) between Military Road and Hickory Street.
Traffic impacts: Military Road is closed between CTH VV (Pioneer Road) and South Seymour Street. The closure for Military Road is tentatively scheduled to be complete in early October. The contractor is planning to switch traffic onto the new concrete of the eastbound lanes of CTH VV (Pioneer Road) near the middle of the week.