County Road V from Pioneer Road to Fond du Lac Avenue Pioneer Road from Sherwood Boulevard to Wedgewood Road
Schedule: April 2019 through October 2019
Description of work: The project includes reconstruction of the water main and services and partnership with Fond du Lac County for new storm sewer, street, pedestrian trail, and lighting.
May 28 th to May 31 st : The contractor has completed water main on Pioneer Road west and east of County Road V.
Traffic impacts: County Road V from Fond du Lac Avenue and Pioneer Road is closed to through traffic. Additionally, Pioneer Road from Sherwood Blvd to Wedgewood Lane is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs.
Project Detour: North on Fond du Lac Avenue to South on Martin Avenue to west on Pioneer Road.
East Cotton Street from North Park Avenue to McKinley Street
Schedule: May 2019 through September 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
May 28 th to May 31 st : The utility contractor will begin installing sanitary sewer at McKinley Street, working west and plan to begin installing water main late in the week.
Traffic Impacts: East Cotton Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
McKinley Street from Rose Avenue to Stow Street
Schedule: May 2019 through September 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
May 28 th to May 31 st : The utility contractor will be installing sanitary and water laterals and storm sewer north of Arndt Street.
Traffic Impacts: Traffic Impacts: McKinley Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Stow Street from McKinley Street to Roosevelt Street
Schedule: May 2019 through September 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
May 28 th to May 31 st : The utility contractor will be installing sanitary and water laterals and storm sewer.
Traffic Impacts: Stow Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Roosevelt Street from Rose Avenue to Arndt Street
Schedule: May 2019 through July 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
May 28 th to May 31 st : The utility contractor will finish installing storm sewer and water main this week.
Traffic Impacts: Roosevelt Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Marquette Street from Arndt Street to McWilliams Street
Schedule: July 2019 through October 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
May 28 th to May 31 st : No work at this time.
Traffic Impacts: Marquette Street remains open to traffic.
Grove Street from Superior Street to South Military Road
Schedule: April 2019 to June 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
May 28 th to May 31 st : The contractor will be placing curb and gutter mid-week.
Traffic Impacts: Grove Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Intersection of Trowbridge Drive and Willow Lawn Road
Schedule: April 2019 to June 2019
Description: The project includes reconstruction of the sanitary, water extension, storm sewer, street, and lighting.
May 28 th to May 31 st : The paving contractor will be fine grading and asphalt paving mid-week.
Traffic Impacts: Intersection of Trowbridge Drive and Willow Lawn Road is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Tompkins Street from Superior Street to Termini
Schedule: April 2019 to June 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
May 28 th to May 31 st : The electrical and curb work was completed and the fine grading and asphalt pavement is scheduled to be completed late in the week.
Traffic Impacts: Tompkins Street from the railroad tracks to Superior Street is closed to through traffic. Residents may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Hickory Street Bridge over West Branch of Fond du Lac River
Schedule: May 2019 through June 2019
Description: The bridge deck will be milled and a new overlay installed which requires the closure of the bridge to vehicle and pedestrian travel.
May 28 th to May 31 st : The contractor completed the concrete bridge deck overlay and is performing a wet cure through mid-week. Some curb and pavement repairs will take place in preparation for the asphalt approaches.
Traffic Impacts: Hickory Street Bridge will be closed to traffic and pedestrian access. Follow the signed detour which is South Bound (SB) – Western Ave. to N. Brook Street to S. Military and North Bound (NB) is the reverse order of SB.
East Second Street Bridge over DeNeveu Creek
Schedule: May 2019 through June 2019
Description: The contractor completed the surface repairs on the bridge deck and sidewalk. An epoxy overlay will be placed which is scheduled to begin mid-June. When the epoxy overlay starts the bridge will be closed for a few weeks. This will restrict vehicle and pedestrian access across the bridge.
May 28 th to May 31 st : No work is anticipated until the epoxy overlay begins in mid-June.
Traffic Impacts: E. Second Street Bridge is currently open to traffic and will remain open until the epoxy overlay work begins mid-June then it will be closed to both vehicle and pedestrian access for several weeks.
Johnson Street, STH 23 from Main Street to Peters Avenue
Schedule: May 20 th through June 7 th
Description: The Department of Public Works crews are removing the brick pavers located in the crosswalks on Johnson Street west of Main Street and completing additional routine maintenance in these blocks.
May 28 th to May 31 st : Crews completed crosswalk work between Main Street and Hickory Street. Crosswalk replacement continues between Hickory Street and Peters Avenue.
Traffic Impacts: Starting early on Tuesday, May 28 th , the traffic control will be moved maintain two way traffic on Johnson Street between Peters Avenue to Hickory Street along the north side of Johnson Street. Crews will replace the south cross walks on Johnson Street like they did along the north side. Traffic at the cross street intersections for north and south streets will be maintained. The lane restrictions between Peters Avenue and Hickory Street are planned to be in place until June 7 th . Pedestrian access will be allow within 24 hours of pouring the crosswalks. Motorists should follow the signed detour in place Hwy 23, to Hwy 41, to Hwy 151.
Arndt Street Bridge Replacement, Arndt Street between Satterlee Street and Lincoln Avenue
Schedule: May 20 th through June 7 th
Description: The project includes the replacement of the Arndt Street Bridge over the West Branch of the Fond Du Lac River. This project is a partnership between the City of Fond du Lac and the Wisconsin Department of Transportation (DOT).
May 28 th to May 31 st : The contractor will begin mobilizing equipment to the site this week. Some work on the bridge demolition may begin by weeks end.
Traffic Impacts: Arndt Street between Lincoln Ave. and Satterlee Street will be closed to traffic beginning Friday, May 31 st for the duration of the project, which is expected to last until Mid-October. There will not be a signed detour but the use of N. Hickory Street to Scott Street to N. Brook Street or the Johnson Street Bridge is