10-21-19 fdl weekly construction schedule

Marquette Street from Arndt Street to McWilliams Street
Schedule: July 2019 through October 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
October 21 st to October 25 th : The concrete contractor will be placing concrete curb and gutter, forming, grading and placing concrete driveways/sidewalk.
Traffic Impacts: Marquette Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Arndt Street Bridge Replacement, Arndt Street between Satterlee Street and Lincoln Avenue
Schedule: June 2019 through October 2019
Description: The project includes the replacement of the Arndt Street Bridge over the West Branch of the Fond Du Lac River. This project is a partnership between the City of Fond du Lac and the Wisconsin Department of Transportation (DOT).
October 21 st to October 25 th : Contractor will install the railing on the new bridge deck and perform miscellaneous cleanup work. The contractor will also have a crew onsite forming and pouring the concrete sidewalks on the east and west ends of the new bridge.
Traffic Impacts: Arndt Street between Lincoln Ave. and Satterlee Street is closed to thru-traffic. Boat traffic under the structure will be restricted at time as work progresses.
County Road V from Pioneer Road to Fond du Lac Avenue Pioneer Road from Sherwood Boulevard to Wedgewood Road
Schedule: April 2019 through end of November 2019
Description of work: The project includes reconstruction of the water main and services and partnership with Fond du Lac County for new storm sewer, street, pedestrian trail, and lighting.
October 21 st to October 25 th : Fond du Lac County Highway Dept will be continuing restoration and backfilling curb and terraces.  Fine grading the existing base will start with potential asphalt pavement installation toward the end of the week pending weather and site conditions.  Electrical contractor continues to install conduit and bases on CTH V’s northern section.  Concrete contractor will be finishing up pouring islands, curb and gutter, approaches, sidewalk, and driveways along CTH V north of CTH VV Pioneer Road.
Traffic impacts: County Road V from Fond du Lac Avenue and Pioneer Road is closed to through traffic. Additionally,  Pioneer Road from Sherwood Blvd to Wedgewood Lane is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Project Detour: North on Fond du Lac Avenue to South on Martin Avenue to west on Pioneer Road.
Traffic Impacts: At the above-mentioned bridges, there will be equipment along the curb line and some lane restrictions are possible. Please be cautious when approaching these bridges.
WIS 23 Resurfacing
Location/Limits: WIS 23 from Town line Road to County VVV Fond du Lac County.
Length of Project: 1.9 miles
Schedule: September 9, 2019 to late November 2019
Cost: $3.4 million
Description of work: This project will resurface WIS 23 in the project limits and add a left-turn and right-turn lane at the intersection of WIS 23 and Esterbrook Drive. Slotted left-turn lanes will be added at the WIS 23/County VVV intersection along with new signal upgrades. Concrete base patching and culvert pipe replacement will be conducted throughout the project limits.
October 21 st to October 25 th :  Final signing, pavement marking, rumble strip, and restoration work will be completed this week.
Traffic impacts: WIS 23 is closed to through traffic from Townline Road to County VVV.
Local and emergency vehicle access to homes and businesses will be maintained throughout the project during the closure. Work will be conducted under flagging operations when the detour is not in place.
Detour: A signed detour will direct westbound WIS 23 traffic north on I-41 to southbound WIS 26 back to westbound  WIS 23. The detour will direct eastbound WIS 23 traffic north on WIS 26 to southbound I-41 back to eastbound WIS  23.

Related Posts

Loading...