Doty Street from Follett Street to Scott Street
Schedule: April 2021 through October 2021
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
November 1 to November 5: Asphalt pavement is scheduled to begin early in the week. Restoration areas will be prepped for topsoil and seeded.
Traffic Impacts: Doty Street remains closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Doty Street is accessible during off hours.
W. Cotton Street from Military Road to Macy Street
Schedule: April 2021 through October 2021
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
November 1 to November 5: Asphalt pavement is scheduled to begin early in the week. Restoration areas will be prepped for topsoil and seeded.
Traffic Impacts: Cotton Street remains closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs WIS 23 Expansion – Urban Section – WI DOT Northeast Region
Location Limits: WIS 23 and various intersecting local roads between US 151 and Seven Hills Road
Schedule: April 19, 2021 to fall of 2022
Description of work: This work is part of the WIS 23 4-lane, on-alignment expansion project in Sheboygan and Fond du Lac counties.
November 1 to November 5: The contractor is scheduled to work on the following items:
Highway 23 eastbound (Wisconsin American Drive to County UU) – Continue curb & gutter, begin concrete
barrier wall, begin topsoil and landscaping, and begin asphalt driveways
Highway 23 westbound (USH 151 to Wisconsin American Drive) – Place curb & gutter, switch traffic to new
lanes, begin grading the median
Highway 23 westbound (County UU to Seven Hills) – Continue concrete paving
County K south of Highway 23/Maryhill Drive – Topsoil and landscaping at new sidewalk, install light poles,
begin asphalt paving, pavement marking and permanent signing
County UU Interchange – Continue placing fill on the interchange
County UU bridge over Highway 23 – Begin pier construction