5-23-22 fdl weekly construction update

2nd Street from Vincent Street to DeNeveu Creek
Schedule: May 16th though October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
May 23 to May 27: Contractor will continue water main installation.
Traffic Impacts: 2nd Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Eighth Street Water Main Replacement
Schedule: May 16th though October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
May 23 to May 27: Contractor will begin water lateral installation.
Traffic Impacts: 8th Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
14th Street Reconstruction
Schedule: May 9 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
May 23 to May 27: The contractor has postponed the start of 14th Street until the week of May 30.
Traffic Impacts: 14th Street remains open to traffic.
Johnson Street Mall Intersections
Schedule: Construction Start April 4-June 2022 – Stage 1 Median
Description: The project includes reconstruction of the median turn lanes and install traffic signals at the west entrance to the mall.
May 23 to May 27: Crews completed the installation of concrete pavement and colored crosswalk at the west Mall entrance. Crews will install traffic signal bases and pull boxes, pave asphalt trail and intersection transition. Concrete sidewalk and curb ramps will be poured by the end of the week, weather pending.
Traffic Impacts: Johnson St. will remain open to two lanes of traffic in each direction at all times. Stage 1 the median work is completed and Stage 2 reconstructs the west entrance to the Mall and installs signals. The west Forest Mall entrance will be closed for Stage 2.
Pioneer Road from Johnson Street to Forest Avenue – FDL County Highway Dept
Schedule: Construction Start April 4- October2022
Description: The reconstruction of Pioneer Rd includes curb and gutter, new storm sewer, water main, street lighting, multi-use trail, and installation of traffic signals on Pioneer Rd between KFC and Faros. Stage 1 work is from the proposed signalized intersection north to Johnson St. Stage 2 is from 400 FT south of Forest Avenue to the signalized intersection.
May 23 to May 27: Water main installation and initial roadway grading is completed. The utility crew will continue installing storm sewer all next week. During storm sewer work there will be equipment, trucks and piping within the roadway. Use caution as you travel through the work zone. There may be times you have to wait a short time for workers and equipment to move to access certain areas. All businesses will remain accessible to the public during grading operations.
Traffic Impacts: Pioneer Rd will be open to “local traffic only” during construction. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. Use “Caution” in the construction zone. Right-in/out access only from Johnson St to Pioneer Rd is required to construct the utilities and the roadway. Customers can access businesses from Pioneer Rd or from the frontage road west of former Home Depot. A signed detour for Pioneer Road will be CTH OOO (Scott St) to CTH VVV (Rolling Meadows) to CTH D (Military Rd).
Military Road from Western Avenue to Superior Street – WI DOT Northeast Region
Schedule: April 11-October 2022 – Stage 1 Military Road/Western Ave Intersection
Description: The reconstruction of S Military Rd includes reconstruction of the street and utilities, addition of bike lane and construction of a roundabout at the intersection of Military Road and 9th Street.
May 23 to May 27: Contractor will start grading the intersection of Military Road and Western Ave. Underground crew will start sanitary sewer work from the intersection of Military Road and Western Ave. working towards Grove Street. Later in the week the contractor is planning on starting to pave the intersection of Military Road and Western Ave. There will be no work next weekend due to the holiday.
Traffic Impacts: Military Road will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. Stage 1 Detour: Southbound on Military Road is east on 2nd Street, south on Main Street, west on 9th Street to Military Road. Northbound detour is signed the same utilizing 9th Street, Main Street, and 2nd Street to Military Road.
WIS 23 Expansion – Urban Section – WI DOT Northeast Region
Location/limits: WIS 23 and various intersecting local roads between US 151 and Seven Hills Road
Schedule: April 11, 2021 to fall of 2022
Description of work: This work is part of the WIS 23 4-lane, on-alignment expansion project in Sheboygan and Fond du Lac counties.
May 23 to May 27: The contractor anticipates working on the following items:

  • Continue grading westbound WIS 23 between Wisconsin American Drive and County UU.
  • Continue shouldering operations on new westbound WIS 23 east of County UU.
  • Continue construction of the new retaining wall under US 151 along the westbound lanes.
  • Continue construction of the new connecting roadway between Hilltop Drive and Whispering Springs Drive.
  • Begin construction of the new westbound bridge over County K.
  • Continue work on the new bridge at County UU.

Traffic impacts:

  • County K north at WIS 23 – Closed
  • County UU (South of WIS 23) – Closed
  • County UU (North of WIS 23) – Closed
  • Irene Drive: During milling and paving operations, please expect minor delays traveling through the worksite.