2 nd Street from Vincent Street to DeNeveu Creek
Schedule: May 16 th though October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
August 29 to September 2: Grading contractor will prep terraces for restoration at the beginning of the week. Restoration contractor will be placing topsoil and seeding terraces following grading contractor.
Traffic Impacts: 2 nd Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
- Butler Street from Russell Street to Portage Street
Schedule: July 7 th though October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
August 29 to September 2: No work is anticipated this week.
Traffic Impacts: N. Butler is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
- Butler Street from Forest Avenue to W. Division Street
Schedule: July 11 th though October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
August 29 to September 2: Sewer contractor will finish storm sewer main installation and begin storm laterals.
Traffic Impacts: S. Butler is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
- Bell Street from Bragg Street to Forest Avenue
Schedule: July 11 th though October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
August 29 to September 2: No work is anticipated this week.
Traffic Impacts: S. Bell is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Grove Street from Hillcrest Lane to Seymour Street
Schedule: June 6 th though October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
August 29 to September 2: Grading contractor will prep terraces for restoration at the end of the week. Restoration contractor will be placing topsoil and seeding terraces following grading contractor.
Traffic Impacts: Grove Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
14 th Street Reconstruction
Schedule: May 31 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
August 29 to September 2: Contractor will continue with storm sewer main and lateral installation. The pipe-bursting contractor will continue installing sanitary laterals and water services.
Traffic Impacts: 14 th Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Military Road from Western Avenue to Superior Street – WI DOT Northeast Region
Schedule: April 11-October 2022
Description: The reconstruction of S Military Rd includes reconstruction of the street and utilities, addition of bike lane and construction of a roundabout at the intersection of Military Road and 9 th Street.
August 29 to September 2: Utility contractor continues working on storm sewer and grading.
Traffic Impacts: Military Road remains closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. The intersection of Military Road and 9th Street remains closed to traffic.
WIS 23 Expansion – Urban Section – WI DOT Northeast Region
Location/limits: WIS 23 and various intersecting local roads between US 151 and Seven Hills Road
Schedule: April 11, 2021 to fall of 2022
Description of work: This work is part of the WIS 23 4-lane, on-alignment expansion project in Sheboygan and Fond du Lac counties.
August 29 to September 2: The contractor anticipates working on the following items:
Continue grading on the WIS 23 eastbound lanes and the new trail from County UU to the east.
Continue storm sewer installation on WIS 23 eastbound east and west of Tower Road.
Begin curb and gutter on County K north of WIS 23.
Continue building the new road on WIS 23 westbound under Highway 151.
Continue construction of the new retaining wall between Hilltop and County UU.
Traffic impacts:
County K north at WIS 23 – Closed
County UU (South of WIS 23) – Closed
County UU (North of WIS 23) – Closed