- Butler Street from Russell Street to Portage Street
Schedule: July 7 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
October 10 to October 14: Concrete contractor will begin pouring sidewalk and driveway aprons
Traffic Impacts: N. Butler is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
- Butler Street from Forest Avenue to W. Division Street
Schedule: July 11 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
October 10 to October 14: Concrete contractor will begin pouring sidewalk and driveway aprons
Traffic Impacts: S. Butler is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
- Bell Street from Bragg Street to Forest Avenue
Schedule: July 11 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
October 10 to October 14: No work is anticipated.
Traffic Impacts: S. Bell is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
14 th Street Reconstruction
Schedule: May 31 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
October 10 to October 14: Contractor will continue grading for sidewalks. Concrete contractor will begin pouring sidewalk and driveway aprons.
Traffic Impacts: 14 th Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
- Division Street from Brooke Street to Moore Street
Schedule: September 26 through November
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
October 10 to October 14: Sewer work will continue.
Traffic Impacts: W. Division Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Lewis Street from Brooke Street to Dead End
Schedule: September 26 through November
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
October 10 to October 14: Contractor will begin storm sewer installation and water main installation.
Traffic Impacts: W. Division Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
2022 Mill ; Overlay Program
Schedule: October 3 through October 21
Description: The project includes manhole adjustments, spot curb and gutter replacement, milling pavement, and overlay of asphalt.
Project Locations:
Grove Street from Hickory Street to Superior Street
Grove Street from Hickory Street, west approximately 520 feet
Hickory Street from Johnson Street to Scott Street
Northwest Way from Van Dyne Road west 215 feet
October 10 to October 14: Contractor will be working on various structure adjustments and repairs.
Traffic Impacts: All streets remain open to traffic.
Military Road from Western Avenue to Superior Street – WI DOT Northeast Region
Schedule: April 11-October 2022
Description: The reconstruction of S Military Rd includes reconstruction of the street and utilities, addition of bike lane and construction of a roundabout at the intersection of Military Road and 9 th Street.
October 10 to October 14: Concrete pavement will be completed and crews will start installing the new concrete sidewalk.
Traffic Impacts: Military Road remains closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. The intersection of Military Road and 9 th Street remains closed to traffic.
WIS 23 Expansion – Urban Section – WI DOT Northeast Region
Location/limits: WIS 23 and various intersecting local roads between US 151 and Seven Hills Road
Schedule: April 11, 2021 to fall of 2022
Description of work: This work is part of the WIS 23 4-lane, on-alignment expansion project in Sheboygan and Fond du Lac counties.
October 10 to October 14: The contractor anticipates working on the following items:
Begin placing concrete barrier wall along WIS 23 westbound from County UU to County K.
Complete asphalt pavement for the new trail along the project
Place gravel shoulders on the new trail along the project.
Continue permanent signing along WIS 23 eastbound and westbound.
Continue permanent pavement marking along WIS 23 eastbound and westbound.
Begin placing concrete sidewalk on the County UU interchange.
Install electrical light bases on the County UU interchange.
Begin placing asphalt, guardrail, and pavement markings on the Highway 151 northbound off ramp to WIS 23.
Begin reconstruction of Ledgewood Drive.
Traffic impacts:
County K north at WIS 23 – Closed
County UU (South of WIS 23) – Closed
County UU (North of WIS 23) – Closed
USH 151 northbound off ramp to WIS 23: Anticipate delays while using the ramp during construction.
WIS 23 EB lane closure from County Lane to the east: Anticipate delays while using WIS 23 eastbound during construction.