5-12-23 fdl construction schedule

Lighthouse Drive – Lakeside Park

Schedule: April through May

Description: The project includes the reconstruction of Lighthouse Drive with new pavement, multi-use path, street  lighting, parking stall layout, restoration, and tree plantings.

May 15 to May 19: Landscaping contractor will continue with restoration. Pavement marking mid-week

Traffic Impacts: Lighthouse Drive is closed to through traffic.

Eleventh Street – Park Avenue to Vine Street

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

May 15 to May 19: No work at this time.

Traffic Impacts: Eleventh Street remains open to traffic.

Division Street – Lincoln Avenue to Railroad Tracts

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

May 15 to May 19: Alliant Energy’s contractor, Intercon, continues replacement of the gas main and services.

Traffic Impacts: Division Street will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Ledgeview Avenue – Park Avenue to Cottage Ave Dead End

Schedule: May 8 through October

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

May 15 to May 19: Contractor will continue sanitary sewer installation from Cottage Ave moving west. Due to depth of sanitary sewer and width of trench, road will be shut off at excavation at the end of each night.

Traffic Impacts: Ledgeview Avenue is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Third Street – Park Avenue to Everett Street

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

May 15 to May 19: No work at this time.

Traffic Impacts: Third Street remains open.

Warner Street – Ruggles Street to Forest Avenue

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

May 15 to May 19: No work at this time.

Traffic Impacts: Warner Street remains open to traffic.

Related Posts

Loading...