Rolling Meadows Drive from Johnson Street to Scott Street –
Start of work June 28th , 2023
Rolling Meadows Drive – Phase 1 –The contractor will begin rehabilitation work on the inside lanes of Rolling Meadows Drive June 29. During this phase, two-way traffic on Rolling Meadows will remain in place; with some crossover traffic restrictions. The contractor anticipates this phase will be completed in a two-week period; however, there will be one week of cure time and traffic restrictions will remain in place during this time.
Rolling Meadows Drive – Phase 2 – Weather pending, Phase 2 will begin the week of August 1st . Phase 2 rehabilitation includes rehabilitation of the outside lane of traffic. Similar to Phase 1, two-way traffic on Rolling Meadows will remain in place. The contractor anticipates Phase 2 work to be completed in two-week period.
Fourth Street from Everett Street to National Avenue – Start of work July 5, 2023
Fourth Street – Phase 1 – The contractor will begin rehabilitation work on the westbound lane of 4 th Street, July 5. During the westbound lane rehabilitation work, traffic will be restricted to eastbound driving only. Residents and motorists will navigate this area as a one-way traffic only. The contractor anticipates this phase will be completed in a two-week period; however, there will be one week of cure time and traffic restrictions will remain in place during this time.
Fourth Street – Phase 2 – Weather pending, Phase 2 will begin the week of August 1st . Phase 2 rehabilitation includes rehabilitation in the eastbound travel lane. Similar to Phase 1, traffic will be restricted to westbound driving only. The contractor anticipates Phase 2 work to be completed in two-week period.