6-30-23 fdl reconstruction schedule

  1. Division Street Bridge (over DeNeveu Creek) and Concrete Rehabilitation

West of Reid Terrace to East of SSM Hospital Intersection

Project Duration: Friday, June 23 to July 21, weather pending

Description: The project includes replacing the deteriorated Division Street Bridge deck overlay, bridge approaches and sidewalk repairs. City crews will be replacing deteriorated concrete pavement east of the bridge in conjunction with the bridge work.

July 3 to July 7: The contractor milled the deck and removed the old concrete overlay. Crew will complete the concrete removal and cleaning the deck. They will then form the ends of the deck in preparation for pouring the new overlay, possibly by the end of the week weather pending. The city crew will complete the replacement of the concrete panels east of the bridge.

Traffic Impacts: Division Street Bridge will be closed to traffic along with one of the sidewalks across the bridge. Project Limits: 100 Feet east and west of the Division Street Bridge

2023 Fond du Lac Concrete Rehabilitation

Schedule: June 28 through August 25

Description: The project includes various concrete pavement, storm inlet, and manhole rehabilitation work. Streets where repair work will occur:

 N Rolling Meadows Drive from Johnson Street to Scott Street

 Fourth Street from Everett Street to National Avenue

July 3 to July 7: Crews will remove deteriorated concrete panels and pouring of concrete patches.

Traffic Impacts: The above streets will have partial closures and lane restriction. Please follow detours in a few locations and be “Cautious” when driving through the work zone, as lane widths are restricted.

Eleventh Street – Park Avenue to Vine Street

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

July 3 to July 7: Alliant Energy’s contractor, Intercon, continues replacement of the gas main and services. Treeo’s will remove terrace trees.

Traffic Impacts: Eleventh Street remains open to traffic.

Division Street – Lincoln Avenue to Railroad Tracks

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

July 3 to July 7: No work anticipated.

Traffic Impacts: Division Street will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Ledgeview Avenue – Park Avenue to Cottage Ave Dead End

Schedule: May 8 through October

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

July 3 to July 7: Contractor will continue installation of sanitary and water laterals.

Traffic Impacts: Ledgeview Avenue is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Third Street – Park Avenue to Everett Street

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

July 3 to July 7: No work at this time.

Traffic Impacts: Third Street remains open.

Warner Street – Ruggles Street to Forest Avenue

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

July 3 to July 7: No work at this time.

Traffic Impacts: Warner Street remains open to traffic.

Related Posts

Loading...