8-7-23 fdl street reconstruction schedule

E Johnson Street Bridge – Over DeNeveu Creek

Description: The project includes bridge restoration…repainting the bridge railing, painting the concrete parapets, curb and gutter, clearing trees and slope restoration. Crews will also install an epoxy overlay on the deck and sidewalk.

August 7 to August 11: Contractor will continue work on the bridge, clearing trees, removing stumps, replacing settled curb, gutter, and installing riprap.

Traffic Impacts: E Johnson Street will remain open to one lane in each direction. The outside lanes will be closed when crews are performing work to allow crews safe access to complete the required work. The traveling public, residents, business owners, and customers may access across bridge, but please reduce speeds and be cautious of other drivers and the crews performing work…Please Drive SAFELY!

2023 Mill & Overlay Program

Schedule: August 7 through September 8

Description: The project includes manhole adjustments, spot curb and gutter replacement, milling pavement, and overlay of asphalt.

Project Locations:

 Roosevelt Street from Arndt Street to Winnebago Drive

 Division Street from Reid Terrace to National Avenue

 Mohawk Avenue from north of Harborview Drive to north of Boat Launch

August 7 to August 11: Contractor will be working on various structure adjustments and repairs.

Traffic Impacts: All streets remain open to traffic.

Eleventh Street – Park Avenue to Vine Street

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

August 7 to August 11: Contractor will begin storm sewer lateral installation and possibly begin road excavation later in the week.

Traffic Impacts: Eleventh Street will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Division Street – Lincoln Avenue to Railroad Tracks

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

August 7 to August 11: Contractor continues storm sewer installation continuing to move west towards Lincoln Ave, then begin installing from Gould St heading east late in the week.

Traffic Impacts: Division Street will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Ledgeview Avenue – Park Avenue to Cottage Ave Dead End

Schedule: May 8 through October

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

August 7 to August 11: Contractor will begin road excavation.

Traffic Impacts: Ledgeview Avenue is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Third Street – Park Avenue to Everett Street

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

August 7 to August 11: Contractor will begin water main installation.

Traffic Impacts: Third Street remains open.

Warner Street – Ruggles Street to Forest Avenue

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

August 7 to August 11: No work at this time.

Traffic Impacts: Warner Street remains open to traffic.