9-18-23 city of fdl street reconstruction schedule

2023 Seal Coating Program

Schedule: August 23 through September 8, weather pending

Description of work: The work will include placing a mixture of liquid asphalt and fine aggregate over the entire street. The application fills small cracks, cover minor road deterioration, and extend the life of the roadway.

September 18 to September 22: The contractor will begin seal coating Wednesday, September 13 and continue through the week, weather pending. Streets not completed this week will be completed the following week.

Traffic impacts:  The streets will be closed to local traffic for periods of time. Parking will not be allowed on the street during the times of street cleaning and micro surfacing. Temporary “No Parking Signs” will be placed along the street.

LOCATIONS OF THE PROJECT

 Pine Tree Drive  Brookfield Boulevard  Pioneer Parkway

Eleventh Street – Park Avenue to Vine Street

Schedule: July 10 through September

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

September 18 to September 22: Contractor will pave asphalt early in the week (weather pending).

Traffic Impacts: Eleventh Street will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Division Street – Lincoln Avenue to Railroad Tracks

Schedule: July 31 through October

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

September 18 to September 22: Contractor will continue sanitary laterals and water service installation.

Traffic Impacts: Division Street will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Ledgeview Avenue – Park Avenue to Cottage Ave Dead End

Schedule: May 8 through September

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

September 18 to September 22: Grading contractor will continue to rough grade terraces. Restoration contractor will continue placing topsoil and seeding terraces and all areas disturbed during construction.

Traffic Impacts: Ledgeview Avenue is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Third Street – Park Avenue to Everett Street

Schedule: August 9 through October

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

September 18 to September 22: Contractor will finish water service and sanitary lateral installation. They will begin storm sewer main installation mid-week.

Traffic Impacts: Third Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Warner Street – Ruggles Street to Forest Avenue

Schedule: August 14 through October

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

September 18 to September 22: Contractor will finish water service and sanitary lateral installation. They will begin storm sewer main installation mid-week.

Traffic Impacts: Warner Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Related Posts

Loading...