11-11-23 fdl weekly construction update

West Division Street Bridge Replacement over West Branch of Fond du lac River

Schedule: September 2023 through May 2024

Description: In partnership with the WI Department of Transportation the project includes replacing the existing bridge structure and approached. Other work includes replacing concrete pavement, sidewalk, storm sewer, grading and restoration and landscaping.

November 13 to November 17: This week the contractor completed the west abutment, southwest retaining wall and started to work on the pier cofferdam.

Traffic Impacts: Division Street will be closed to vehicle and resident foot traffic from Brooke Street to Tallmadge until spring of 2024. Residents, business owners, and customers should find an alternate route. There is no signed detour as part of this project. Parking is not permitted in the project area as the road is closed.

Alleyway – First Street to Sheboygan Street

Schedule: September 25 through October 2023

Description: The project includes gas main and service relocations, reconstruction of storm sewer, water main, roadway, restoration/landscaping.

November 13 to November 17: Contractor will pave asphalt early next week.

Traffic Impacts: The Alleyway is closed to through traffic. Pedestrians may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs.

Division Street – Lincoln Avenue to Railroad Tracks

Schedule: July 31 through October 2023

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

November 13 to November 17: Contractor will pave asphalt returns and driveways mid-week next week. Terrace restoration to follow.

Traffic Impacts: Division Street will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Warner Street – Ruggles Street to Forest Avenue

Schedule: August 9 through October 2023

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

November 13 to November 17: Contractor will pave asphalt early next week.

Traffic Impacts: Warner Street is closed to through traffic. Residents, business owners, and customers may access  properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move  any construction barricades. Parking is not permitted on the street within the construction zone during working  hours.