6-22-24 fdl street reconstruction schedule

download-1162

Pioneer Road – Martin Avenue to CTH V

Schedule: April 24 through September 28, 2024

Description: The WI Dept of Transportation, along with Fond du Lac County, and the City of Fond du Lac awarded this  project to Vinton Construction. Construction includes common excavation, sanitary sewer, watermain, storm sewer, concrete sidewalk and curb & gutter, an asphalt pedestrian path and roadway, traffic signals &  roadway lighting, permanent signing, and other incidentals.

June 24 to June 28: The contractor completed water service laterals and started installation of storm sewer.

Traffic Impacts: Pioneer Road (CTH VV) is closed to through traffic for the duration of the project.

Detour is as follows: Park Avenue to 9th Street to FDL Avenue to CTH V and vice versa

Marquette Street –

Rees Street – Main Street to Marquette Street

Merrill Avenue to Johnson Street

Schedule: April 15 through October

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

June 24 to June 28: Contractor will finish working on storm main and lateral installation on Rees Street. Road excavation will begin on Marquette Street later in the week. Private side contractor may begin work next week.

Traffic Impacts: Rees Street and Marquette Street are closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Doty Street – W. Division Street to Bridge

Schedule: April 15 through October

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

June 24 to June 28: Contractor will begin rough grading terrace, topsoil placement, seeding and hydromulch will follow.

Traffic Impacts: Doty Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

  1. Division Street – Brooke Street to Tallmadge Street

Schedule: May 2024 through June

Description: The project includes roadway, sidewalk and approaches, street lighting and restoration/landscaping

June 24 to June 28: Concrete contractor will continue pouring concrete pavement.

Traffic Impacts: Division Street will be closed to vehicle and resident foot traffic from Brooke Street to Tallmadge  Street until July 2024. Residents, business owners, and customers should find an alternate route. There is no signed detour as part of this project. Parking is not permitted in the project area as the road is closed.

Ledgeview Avenue – Amory Street to N. Park Avenue

Schedule: May 2024 through August

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

June 24 to June 28: Contractor will continue with sanitary and water lateral installation. Concrete contractor will begin forming and pouring concrete pavement for 2nd stage of Park Avenue.

Traffic Impacts: Ledgeview Avenue will be closed to vehicle and resident foot traffic from Amory Street to N. Park  Avenue until August 2024. Residents, business owners, and customers should find an alternate route. There will be a signed detour for a portion of N. Park Avenue work as part of this project. Parking is not permitted in the project area as the road is closed.

  1. 9 th Street – Bridge to Linden Street

Schedule: June 2024 through September

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

June 24 to June 28: Contractor will begin breaking pavement on 9 th Street on Tuesday. Sewer Contractor would begin  mobilizing equipment on site. Sewer work may begin later in the week.

Traffic Impacts: W. 9 th Street is closed to through traffic. Residents, business owners, and customers may access  properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move  any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Related Posts

All articles loaded
No more articles to load
Loading...