8-10-24 fdl weekly construction update

Pioneer Road – Martin Avenue to CTH V

Schedule: April 24 through September 28, 2024

Description: The WI Dept of Transportation, along with Fond du Lac County, and the City of Fond du Lac awarded this project to Vinton Construction. Construction includes common excavation, sanitary sewer, watermain, storm sewer, concrete sidewalk and curb & gutter, an asphalt pedestrian path and roadway, traffic signals & roadway lighting.

August 12 to August 16: The contractor will continue and finish roadway grading operations on CTH VV. The electrical contractor will begin conduit installation.

Traffic Impacts: Pioneer Road (CTH VV) is closed to through traffic for the duration of the project.

Rees Street – Main Street to Marquette Street

Marquette Street – Merrill Avenue to Johnson Street

Schedule: April 15 through October

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

August 12 to August 16: Private side contractor will continue work behind walk.

Traffic Impacts: Rees Street and Marquette Street are closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Ledgeview Avenue – Amory Street to N. Park Avenue

Schedule: May 2024 through August

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

August 12 to August 16: Concrete contractor will begin slipping curb and gutter and pouring sidewalk and driveway aprons.

Traffic Impacts: Ledgeview Avenue will be closed to vehicle and resident foot traffic from Amory Street to N. Park  Avenue until August 2024. Residents, business owners, and customers should find an alternate route. Parking is not permitted in the project area as the road is closed.

  1. 9 th Street – Bridge to Linden Street

Schedule: June 2024 through September

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

August 12 to August 16: Excavating contractor will finish excavating road to subgrade and placing aggregate.

Traffic Impacts: W. 9 th Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

S Military Road – Superior Street to Hickory Street

Schedule: July 2024 through November

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

August 12 to August 16: Jack and bore operation at the railroad will continue.

Traffic Impacts: S Military Road is closed to through traffic. Residents, business owners, and customers may access  properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours. There will be a signed detour route in place.

Bragg Street – Bell Street to Warner Street

Schedule: July 2024 through November

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

August 12 to August 16: No work anticipated.

Traffic Impacts: Bragg Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Henning Street – Military Rd to Dead End

Schedule: July 2024 through November

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

August 12 to August 16: Contractor will continue sanitary and water lateral installation. Storm sewer will begin later in the week.

Traffic Impacts: Henning Street is closed to through traffic. Residents, business owners, and customers may access  properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move  any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Franklin Street – N. Hickory Street to Henry Street

Schedule: August 2024 through November

Description: The project includes water main and lateral reconnections, roadway, and restoration/landscaping.

August 12 to August 16: Contractor will begin water main installation.

Traffic Impacts: Franklin Street is closed to through traffic. Residents, business owners, and customers may access  properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move  any construction barricades. Parking is not permitted on the street within the construction zone during working  hours.