Pioneer Road – Martin Avenue to CTH V
Schedule: April 24 through September 28, 2024
Description: Construction includes common excavation, sanitary sewer, watermain, storm sewer, concrete sidewalk and curb & gutter, an asphalt pedestrian path and roadway, traffic signals & roadway lighting.
September 3 to September 6: Concrete pavement will continue to be poured on Martin Ave and concrete sidewalk will also be formed poured at the end of the week and into the week after.
Traffic Impacts: Pioneer Road (CTH VV) is closed to through traffic for the duration of the project.
US 45 Improvements in Fond du Lac County
Location/limits: US 45 from Scott Street in the village of North Fond du Lac to the North County Line in the town of Friendship, Fond du Lac County
Schedule: August 26 th to Early November
Description of work: The work under this contract shall consist of asphalt paving, beam guard replacement, culvert replacement, pavement marking, and all incidental items necessary to complete the work as shown on the plans and included in the proposal and contract.
September 3 to September 6: Crews will continue working on replacing cross culverts along US 45 and grading at various beam guard locations.
Traffic impacts: US 45 is open to traffic. Work will be conducted under lane closures with flagging operations.
2024 Mill & Overlay Program
Schedule: August 26 through Mid-September
Description: The project includes manhole adjustments, spot curb and gutter replacement, milling pavement, and overlay of asphalt.
Project Locations:
West Cotton Street from Brooke Street, west to Dead End
West McWilliams Street from Brooke Street, west to Dead End
Wisconsin American Drive from Johnson Street, south to Aurora Urgent Care Entrance
o Resurfacing will occur in two phases to allow for continued traffic to businesses/property owners
located on Wisconsin American Drive and Lynn Avenue
Candy Lane from Eighth Street to Fifth Street – Weather Depending
o Paving – Week of August 26
Fifth Street from Woodward Street, west to entrance of Roberts Elementary School
o Paving – Week of August 26
2024 Seal Coating Program
Schedule: August 26 through August 30
Description of work: The work will include placing a mixture of liquid asphalt and fine aggregate over the entire street. The application fills small cracks, cover minor road deterioration, and extend the life of the roadway.
September 3 to September 6: The contractor will begin seal coating and continue through the week, weather pending. Streets not completed this week will be completed the following week.
Traffic impacts: The streets will be closed to local traffic for periods of time. Parking will not be allowed on the street during the times of street cleaning and micro surfacing. Temporary “No Parking Signs” will be placed along the street. Project Locations:
T-Bird Drive Cougar Court Malibu Court
Winchester Avenue Sammy Jo Circle Churchill Lane
Sycamore Tree Drive Sycamore Tree Court
Rees Street – Main Street to Marquette Street
Marquette Street – Merrill Avenue to Johnson Street
Schedule: April 15 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
September 3 to September 6: No work anticipated.
Traffic Impacts: Rees Street and Marquette Street are closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Ledgeview Avenue – Amory Street to N. Park Avenue
Schedule: May 2024 through August
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
September 3 to September 6: Restoration contractor will begin placing topsoil in terrace areas. Electrical Contractor will install lights and access boxes at the end of the week.
Traffic Impacts: Ledgeview Avenue will be closed to vehicle and resident foot traffic from Amory Street to N. Park Avenue until August 2024. Residents, business owners, and customers should find an alternate route. Parking is not permitted in the project area as the road is closed.
- 9 th Street – Bridge to Linden Street
Schedule: June 2024 through September
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
September 3 to September 6: Concrete contractor will begin concrete curb and sidewalk. Electrical Contractor will install light pole bases at the end of the week.
Traffic Impacts: W. 9 th Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
S Military Road – Superior Street to Hickory Street
Schedule: July 2024 through November
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
September 3 to September 6: Sanitary, Storm, and Water main installation will continue in the intersection of Hickory St. Sanitary and Water laterals will be installed on Military Rd.
Traffic Impacts: S Military Road is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours. There will be a signed detour route in place.
Bragg Street – Bell Street to Warner Street
Schedule: July 2024 through November
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
September 3 to September 6: Electrical Contractor will install conduit at the end of the week.
Traffic Impacts: Bragg Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Henning Street – Military Rd to Dead End
Schedule: July 2024 through November
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
September 3 to September 6: Electrical Contractor will install conduit at the end of the week.
Traffic Impacts: Henning Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Franklin Street – N. Hickory Street to Henry Street
Schedule: August 2024 through November
Description: The project includes water main and lateral reconnections, roadway, and restoration/landscaping. September 3 to September 6: No work anticipated.
Traffic Impacts: Franklin Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.