9-16-24 fdl street reconstruction update

Lakeside Park Pedestrian Bridge Replacement – Oven to Fountain Island

Schedule: September 16 through November 15, 2024

Description: Construction includes removal of the existing wood bridge structure, pouring new concrete abutments and setting a new steel truss bridge.  Site grading, restoration and asphalt pedestrian path will be replaced.

September 16 to September 20: Crews will mobilize to the site, setup the crane and begin removing the old structure.  Barges will be utilized to allow the crane to reach Fountain Island from Oven Island.  This will restrict access through the lagoon channel to Lake Winnebago.

Traffic Impacts: The boat launch off E. Harbor View Dr. will be closed for boats to access Lake Winnebago from Sep. 16 th through Nov. 2024

Pioneer Road – Martin Avenue to CTH V

Schedule: April 24 through September 28, 2024

Description: Construction includes common excavation, sanitary sewer, watermain, storm sewer, concrete sidewalk and curb & gutter, an asphalt pedestrian path and roadway, traffic signals & roadway lighting.

September 16 to September 20: The contractor will pave the roadway and the pedestrian trail with asphalt.

Traffic Impacts: Pioneer Road (CTH VV) is closed to through traffic for the duration of the project.

US 45 Improvements in Fond du Lac County

Location/limits: US 45 from Scott Street in the village of North Fond du Lac to the North County Line in the town of Friendship, Fond du Lac County

Schedule: August 26 th to Early November

Description of work: The work under this contract shall consist of asphalt paving, beam guard replacement, culvert replacement, pavement marking, and all incidental items.

September 16 to September 20: Crews will finish working on driveway culverts along US 45 and grading at various beam guard locations.

Traffic impacts: US 45 is open to traffic. Work will be conducted under lane closures with flagging operations.

Rees Street – Main Street to Marquette Street

September 16 to September 20: Concrete contractor will begin placing curb on the south side of Rees St and West side of Marquette Street mid-week.

Traffic Impacts: Rees Street and Marquette Street are closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Ledgeview Avenue – Amory Street to N. Park Avenue

Schedule: May 2024 through August

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

September 16 to September 20: Asphalt paving will occur sometime during the week.

Traffic Impacts: Ledgeview Avenue will be closed to vehicle and resident foot traffic from Amory Street to N. Park Avenue until August 2024. Residents, business owners, and customers should find an alternate route. Parking is not permitted in the project area as the road is closed.

  1. 9 th Street – Bridge to Linden Street

Schedule: June 2024 through September

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

September 16 to September 20: Concrete contractor will finish the EB and WB pavement from Linden Street through east Aquatic Center Driveway.

Traffic Impacts: W. 9 th Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

S Military Road – Superior Street to Hickory Street

Schedule: July 2024 through November

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

September 16 to September 20: Storm and Water main installation will continue in the intersection of Hickory St. Storm Sewer work will be completed on the east side of Railroad.

Traffic Impacts: S Military Road is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours. There will be a signed detour route in place.

Bragg Street – Bell Street to Warner Street

Schedule: July 2024 through November

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

September 16 to September 20: No work anticipated.

Traffic Impacts: Bragg Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Henning Street – Military Rd to Dead End

Schedule: July 2024 through November

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals,  storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

September 16 to September 20: No work anticipated.

Traffic Impacts: Henning Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Franklin Street – N. Hickory Street to Henry Street

Schedule: August 2024 through November

Description: The project includes water main and lateral reconnections, roadway, and restoration/landscaping.

September 16 to September 20: No work anticipated.

Traffic Impacts: Franklin Street is closed to through traffic. Residents, business owners, and customers may access  properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move  any construction barricades. Parking is not permitted on the street within the construction zone during working hours.