11-2-24 city of fdl weekly construction update

Lakeside Park Pedestrian Bridge Replacement – Oven to Fountain Island

Schedule: September 16 through November 15, 2024

Description: Construction includes removal of the existing wood bridge structure, pouring new concrete abutments and setting a new steel truss bridge.  Site grading, restoration and asphalt pedestrian path will be replaced.

November 4 to November 8: The project is on hold awaiting delivery of the bridge in mid to late December.

US 45 Improvement in Fond du Lac County

Schedule: August 26 th to Early November

Description of work: The work under this contract shall consist of asphalt paving, beam guard replacement, culvert replacement, pavement marking, and all incidental items.

November 4 to November 8: Beam guard replacement will be completed along with pavement marking

Traffic impacts: US 45 is open to traffic. Work will be conducted under lane closures with flagging operations.

S Military Road – Superior Street to Hickory Street

Schedule: July 2024 through November

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

November 4 to November 8: Weathering pending, the concrete contractor will continue placement of curb on pavement that has cure.

Traffic Impacts: S Military Road is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades.