- Main Street from Merrill Ave. to Johnson Street and Merrill Ave. from Portland to Macy Street
Schedule: March 2020 through July 2020
Description: The project includes reconstruction of the storm force main, sanitary laterals, water main and laterals, storm sewer, roadway, sidewalk and approaches, restoration/landscaping, signals and lighting.
May 11 to May 15: The utility crews completed the remaining utility work along N. Main Street and Merrill Avenue. The grading crew will continue removing concrete pavement next week. Crews will then begin excavation and placing breaker run and gravel base course on N. Main Street and Merrill Avenue.
Traffic Impacts: N. Main Street and Merrill Avenue remains closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Detour: A signed detour will direct southbound N. Main Street traffic east on Johnson Street to Park Avenue to Division Street and back to N. Main Street. Similarly, northbound traffic directed eastbound to Division Street to Park Avenue and then to Johnson Street and back to N. Main Street.
Business Signs: Business patrons are encouraged to follow business signs, which will direct them to access drives located adjacent to the businesses. Businesses on the east side of N. Main Street will have access from the east,
Marquette Street to Rees Street and from the west side, Macy Street to Rees Street.
- Military Road from Oak Park Avenue to S. Hickory Street
Schedule: March 2020 through October 2020
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, and restoration/landscaping.
May 11 to May 15: The utility contractor continues to install the water main between Arlington Avenue and Seymour Street. A second crew will begin installing laterals between Arlington and Hickory. Evolution Communications will be working between Oak Park Avenue and Hickory Street rerouting unground cable for Charter Communications.
Traffic Impacts: S. Military Road remains closed to through traffic from S. Hickory Street to Seymour Street. Residents, business owners, and customers may access properties and businesses past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours. Motorists are asked to please use caution when driving through this construction area.
South Main Street Pedestrian Trail – Main Street to Camelot Drive
Schedule: May 2020 through June 2020
Description: The project include the construction of a pedestrian bike path on the west side of Main Street.
May 11 to May 15: The contractor will begin excavation for the new pedestrian trail.
Traffic Impacts: S Main Street will remain open to through traffic with traffic; the contractor will be utilizing the parking lane with equipment for southbound Main Street.
County Road V/Fond du Lac Avenue/National Avenue
Schedule: March 2020 through October 2020
Description of work: The project includes reconstruction of the water main and services and partnership with Fond du Lac County for new storm sewer, street, pedestrian trail, and lighting.
May 11 to May 15: Fond du Lac County Highway Dept will begin work on storm sewer installation.
Traffic impacts: The intersections of County Road V/Fond du Lac Avenue/National Avenue remain closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs.
Project Detour: Signed detour in place utilizing Pioneer Road, Martin Avenue, and Ninth Street